Bottletree Release
Wrapping around a brand new 7,500sqm community park, the Bottletree Release offers purchasers a variety of land lots that will enjoy park frontage and green views from the comfort of their own home.
Families, first home buyers and downsizers alike will enjoy the health and wellbeing benefits afforded by living within proximity of green open space.
Estimated title date May 2024
Information correct as at 27-03-2024
Update - March 2024
Progress has been strong through Stage 3, with base layers of roads being built up in preparation for asphalt. With all services complete internal to the Stage, work is progressing on Concrete paving for footpaths and laneways.
Wetland works are also progressing well with the second sed basin almost complete. The Waterway is not without its' challenges, but the team are making good progress with most excavation work complete and rock beaches following them through.
The fine weather of late has helped and if this continues through March, we are on track to reach Practical Completion in early April.
Titles are anticipated in May for Stage 3
- Practical Completion anticipated early April
- Statement of Compliance anticipated mid-late April
- Settlements anticipated end of April/early May